The BCIS CapX featured project for November 2020, submitted by Renfrewshire Council, is the recently completed £1.91m early learning and childcare centre in Strathclyde.
The project was procured as a design and build using the SBCC Design and Build Contract 2011.
The single storey ‘L’ shaped on plan 535m2 early learning and childcare centre providing 128Nr placed for children aged 3 to 5 years old, comprises:
These areas equate to:
The building cost at £2,020/m2 (1Q2019), compares with the average of £2,251/m2 for 107 nursery school projects on the same basis on the BCIS Online database. The functional unit cost equates to £8,442.68/pupil place.
Substructure, at £177/m2 includes:
Superstructure, at £747/m2 includes:
Finishes, at £137/m2 include:
Fittings and furnishings, at £115/m2 include:
Services, at £814/m2 include:
Prefabricated Buildings, at £30/m2 include:
External and facilitating works at a cost of £576,027 include:
The £/m2 figures include preliminaries at 15.19%.
BCIS would like to thank Renfrewshire Council for providing the data and all those who have submitted projects to be published online.
Cost analyses are available as part of the BCIS Online service.
BCIS regularly receives projects where the contract comprises buildings with different functions that are analysed as complex contracts within the BCIS database. Every effort is made to prepare a separate analysis for each building type and each analysis shows the total scope and cost of the contract, which will influence the pricing levels.
Each analysis is cross-referenced to the other analyses in the contract, which allows BCIS to capture separate analyses, £/m² rates and functional unit rates appropriate to each building, e.g. number of vehicle spaces. The functional unit rate is the total cost of the building excluding external works, with preliminaries apportioned by value and divided by the appropriate functional unit.
BCIS CapX is an industry repository for building project costs analysed elementally. It provides clients, consultants and contractors secure online access to their project data. The analyses can be prepared from contract documents used in most procurement routes, for example:
Find out how you can submit your projects and take part in our surveys